Fujifilm Dimatix asked EV to increase parking capacity at their Lebanon, NH facility. A 40-space parking facility was designed to be constructed above the existing loading area. The project was challenging due to the parking lot location being up-slope, existing wetlands and minimal existing stormwater infrastructure to tie in to.
EV designed a two-chamber stormwater system and was able to discharge the system into existing infrastructure. The project was designed so that operations at 7 Commerce would be minimally disturbed during construction and so that loading activities could continue during construction and at completion of the project. The project was approved by the Lebanon, NH Planning Board, the DPW and is now in the construction stage.